Floor Layers, November 2007
Removed old carpet and installed new carpet squares in the Construction Academy Building (old Firehouse).
Painters, November 2007
Completed painting the exterior of Building 3 and began painting exterior of Building 24..
Masons, November 2007
Cleared, formed and poured slabs for DISL parts washer and lunch/break areas for AMT and DISL.
Masons, October 2007
Filled and sealed expansion joint in Building 27 mauka entrance which was hollowed out by a water main rupture..
Electricians, October 2007
Responded to call from COSM that there was a strong smell of what seemed to be burning electrical wires in their dispensary room. The electricians did a thorough investigation, pinpointed the problem to a malfunctioning old refrigerator and cut the electrical service to this appliance..
Carpenters, October 2007
Removed and replaced fence railings in the Childcare Center playground and constructed and installed six planters along the Center walkways..
Masons, September 2007
Removed old tile, extensive preparation of old and damaged wall and replaced ceramic tile in Building 20 Women’s Restroom..
Roofers, September 2007
Applied non-skid surface material to the Ewa entrance to Building 6 and to the steps leading up to the Building 71 (ETC portables) walkways..
Tapers, September 2007
Taped and patched holes in Building 2, Room 416 which be converted into the MELE program studio..
Floor Layers, September 2007
Installed industrial grade carpet, padding and cove base molding in Building 2, Room 416 which will be converted into the MELE program studio..
Plumbers (Local 675), September 2007
Removed and capped plumbing in Building 2, Room 416 which will be converted into the MELE program studio..
Electricians (Local 368), September 2007
Repaired electrical outlets in the Carpentry Yard and installed new outlets in the Carpentry Shop..
Electricians (Local 368), September 2007
Removed and relocated electrical outlets in Building 2, Room 416 which will be converted into the MELE program studio..
Carpenters, September 2007
Demolished counter and sink unit and patched drywall in Building 2, Room 416 which will be converted into the MELE program studio..
Carpenters, September 2007
Repaired the walkway and floor in the trailer located in the back of RAC which serves as the City and County training program classroom. .
Masons, September 2007
Poured a concrete slab in the Diesel Program parking lot to relocate their picnic table. Also, poured another slab to serve as a platform for their new parts washer..
Masons, September 2007
Removed, leveled ground and replaced pavers in front of the Student Lounge which were pushed up by tree roots..
Masons, September 2007
Demolished and re-poured sidewalk that runs from the mall to Building 2 (along the Student Lounge) that had been lifted by tree roots..
Carptenters, August 2007
Built a message “sandwich advertising board” for the PRIDE program in Building 5 courtyard..
Masons, August 2007
Added four courses of tile block to the top of the existing wall that borders the mauka end of Parking Lot 3..
Masons, May 2007
Removed and replaced ceramic tile on walls and floor in special needs restroom in Building 20.
Plumbers and Fitters, April 2007
Replaced compressor in air conditioning unit which services Building 4, Room 23B.
Masons, April 2007
Removed and replaced ceramic tile on the walls and floor in the men's restroom in Building 20.
Plumbers and Fitters, March 2007
Ran piping for compressed air from compressor to new plasma cutter in the Sheet Metal shop.
Electricians (Local 368), March 2007
Installed two electrical outlets in the Masons training area behind Building 12.
Carpenters and Construction Academy, March 2007
Reinforced and installed new floor on mezzanine in Maintenance Building.
Construction Academy, March 2007
Installed molding in HCC Childcare Center to secure vinyl floor covering.
Masons, February 2007
Removed and replaced broken floor ceramic tile and extended and tiled platform for steamers in the cafeteria.
Ironworkers (Jeff Lane), January 2007
Repaired (re-welded) broken stainless steel counter rack in the cafeteria.
Masons, November 2006
Re-tiled ABRP faculty shower.
Plumbers (ABC), November 2006
Replaced plumbing fixtures in ABRP faculty shower.
Plumbers (ABC), November 2006
Modified plumbing to re-position cooking steamers in the cafeteria kitchen.
Masons, November 2006
Repaired crack in sidewalk leading to Building 2 and recaulked the expansion joints in the concrete walkway in front of the Library.
Carpenters, October 2006
Built and installed gate in childcare center walkway.
Masons, October 2006
Removed and replaced broken and loose floor ceramic tile in the cafeteria kitchen.
Masons, October 2006
Recaulked the expansion joints in the concrete walkway in the back of the Library.
Masons, October 2006
Patched uneven areas in the sidewalk in front of the Library which were tripping hazards.
Masons, October 2006
Removed portions of concrete in Building 5 courtyard that were pushed up by tree roots creating tripping hazards and from an area which was too steep for wheelchairs. Leveled out these areas with new concrete.
Masons, September 2006
Poured decorative slab for the campus map stand near Building 14.
Carpenters, September - October 2006
Built frames, sized maps and mounted campus maps in Building 7 shelter, on Building 4 wall and near Building 14.
Painters, September - December 2006
Continued painting exterior of Building 3.
Masons, September 2006
Removed and replaced large broken and uneven portions of concrete in the Building 5 Courtyard.
Electricians(Local 368), September 2006
Repaired two broken electrical outlets in the carpenters' concrete form training area in the Kokea Apartments parking lot.
Painters, January - May 2006
Painted the front and one side of the ABRP building.
Electricians (Local 368), May 2006
Repositioned all ceiling fluorescent lights in Building 5, Room 202.
Electricians (Local 1186), May 2006
Hard wired ceiling projector in Building 2, Room 616.
Masons, April 2006
Replaced ceramic tiles on benches in front of the cafeteria.
Carpenters, ABRP and SMP, March 2006
Finished and installed campus map stand on Dillingham Blvd.
Masons, February and April 2006
Removed and replaced asphalt sidewalks with concrete sidewalks (mall to childcare center).
Glaziers, February 2006
Provided and cut glass tops for desks in Administration.
Masons, February 2006
Poured a slab of concrete in child care playground.
Masons, February 2006
Poured concrete slab for campus map located on Dillingham Boulevard between ABRP and ETC.
Carpenters, January 2006
Renovated office spaces in Apprenticeship Office.
Glaziers, January 2006
Removed and replaced 16' of full length mirrors in Apprenticeship Conference Room.
Masons, January 2006
Reset sunken pavers around gazebo in front of Building 6.
Masons, January 2006
Erected three tile columns to support sidewalk concrete overhang and demolished old existing tile wall surrounds - Building 20 Ewa entrance.
Masons, January - February 2006
Demolished and rebuilt tile enclosure around the electrical transformer between Buildings 20 and 14.
Masons, January 2006
Laid slate on 9-11 monument and walkway.
Masons, January 2006
Replaced slate on Berlin Wall Monument walkway.